By Andy Nathan, Creative Smart Contractors
Two hours a day. That’s how long one big condo building let us make noise.
It was a high-rise right off Lake Shore Drive. The job should have taken one eight-hour day. With the two-hour rule, it took five.
Then there was parking. Right off Lake Shore Drive, there’s no place for contractors to park. We had two trucks. So we paid for parking five days instead of one. That’s five times the parking bill.
My crew gets paid by the day, too. So we paid them for five days, not one. A one-day job ended up costing about five times as much.
Nobody saw that coming. Not us, and not the owner.
That’s what a condo can do to a remodel when you don’t know the rules first. The good news? You can avoid most of it. Here’s how to do that in your Lakeview condo.
Read the building rules before you sign anything
Every building has its own rules. Most have set work hours. A lot of them don’t allow weekend work. Some only let you use the elevator at certain times.
Ask your building manager for the rules in writing. Look at the work hours first. If they’re short, your job will take longer. It’ll probably cost more, too.
Most boards also want paperwork before you start. That’s usually your plans, your contractor’s insurance, and a signed agreement. Some want a deposit. Approval can take days or even weeks. So send it in early. Don’t wait until you’ve picked your tile.
Know who really makes the call
We had a condo job on Marine Drive that just stopped. The board wasn’t the problem. The maintenance man was.
He held everything up, and we didn’t know what to do. Honestly, we got so frustrated we joked about what it would take to get him moving.
Then we did the simple thing. We went to the board directly. They said, “You guys can go forward.” That was it.
So if your job gets stuck, go to the board or the management company. Put it in writing. Get a clear yes.
Your neighbors can stop your job
In a condo, you share walls, floors, and ceilings with people. Noise travels.
On a rehab we did in Fulton Market, the people below us got tired of the noise. They complained, and it caused a problem with the building. We lost the elevator and had to apply for it all over again. The job just sat there and waited.
A little kindness goes a long way. Leave your neighbors a note before you start. Tell them the dates and the hours. Keep the halls clean every day. It’s small stuff, but it keeps people from calling the manager.
Pipes, risers, and permits
Your pipes connect to your neighbors’ pipes. The big water lines that run up through the building are called risers. Sometimes we have to shut one off to do plumbing work. That can cut the water for part of the building.
We’re on a job like that right now. The association said yes. They even gave us an HOA letter. We still needed a city permit.
That’s the rule. If you shut off a riser for the whole building, or even part of it, you need a permit. The HOA letter isn’t enough.
The cheapest fix: don’t move things

Here’s a Lakeview condo kitchen we finished this year. We didn’t move a single wall. We left the plumbing and other mechanicals right where they were. We even kept the same bay window.
That’s the number one way to keep kitchen costs down. You save on permits and architects. You save time, too.

There are two questions I’d ask before you get any quote.
First, does my floor run under my cabinets? In this kitchen, the old tile did. That makes the floor and the cabinets one job, not two. It can change your price by thousands.
Second, how will the new floor meet the old one? Here, the wood floor in the hall stayed. So we finished the edge with a flush metal strip. Done wrong, you get a lip you’ll stub your toe on for years. It’s the last thing on the last day, so it gets rushed. Ask about it up front.

How long does a condo bathroom really take?
Right now we’re doing two condo bathrooms on Roscoe in Lakeview. We’re doing them one at a time.
The first one passed its rough inspection last week. We’re patching walls now. Final inspection should be next week. That’s about four to five weeks so far.
All in, a condo bathroom takes us about six to seven weeks. But our actual work is only two to three weeks.
The rest is waiting on permits and inspections. That adds at least two to three weeks, and sometimes more. We’ve waited six weeks on an electrical permit before. So plan for the permit clock, not just the work clock.
Want a quick idea of what your bathroom will cost? Schedule a free estimate today with our team.
Is it worth it?

I won’t lie to you. The middle of a remodel is rough. There’s dust everywhere, and your kitchen is gone for a while.
But when we’re done, I hear the same thing over and over. “Wow, this is amazing. I can stay where I’m at.”
That’s what we mean by Don’t Move. Improve.
It can help when you sell, too. I’m a licensed Realtor, and kitchens and baths are great for resale. In Chicago, a minor kitchen remodel got back about 94% of its cost. A midrange bathroom got back about 66%. Those numbers come from the 2025 Cost vs. Value report.
Ready to start?
A Lakeview condo remodel takes some planning. But you don’t have to pay five times what you planned.
Book a free estimate here. You’ll talk to me, the owner. Not a salesman.
Contact Andy Nathan
Andy Nathan
Creative Smart Contractors, LLC
City of Chicago License #TCG133460
312-635-5340
Chicago, IL
Andy Nathan
Real Estate Broker
Realtor® – License # 471.022171
Pearson Realty Group
1000 N. Milwaukee Ave
Chicago, IL 60642
o. 773.325.2800
c. 847.710.7093
andy@pearsonrealtygroup.com
www.pearsonrealtygroup.com