Bally’s Chicago has announced $560 million in financing as construction continues on its permanent casino in River West. But while the casino is still targeting a spring 2027 opening, the development’s 34-story hotel remains delayed, with no announced completion date.

New financing for the casino project
Announced November 17, the financing package includes $500 million in second-lien loans intended primarily to refinance existing debt and support operations, plus an additional $60 million commitment from Gaming and Leisure Properties toward development. The new funding is a significant step for a project facing both substantial remaining construction costs and financial pressures.
What about the hotel?
The planned 500-room hotel has been moved into a later phase of the development. Its tower is visibly taking shape, and exterior work has progressed, but that does not mean the rooms will be ready when the casino opens. Bally’s has not provided a firm hotel opening date.
The distinction matters: the casino may welcome its first guests while its prominent hotel tower is still unfinished. Other restaurants and amenities are also expected to arrive in stages.
Casino opening still targeted for spring 2027
The permanent casino, being built at the former Chicago Tribune printing plant site along the Chicago River, was originally expected to open in September 2026. The current target is spring 2027, though construction schedules can change.
For Chicago, the stakes are substantial. City officials have counted on the permanent casino to produce major tax revenue, while neighbors continue watching the scale and timing of this massive River West redevelopment.
Bottom line: Bally’s has secured an important new financing commitment, but it has not announced that the hotel delay is over. The casino and hotel now have separate timelines.
Sources: Bally’s November 17 financing announcement; reporting by the Chicago Sun-Times.